APPLICATION OF
CRITICAL CHAIN ON HIGH
VALUE PETROCHEMICAL PROJECTS
Brandon J Loots
Krupp Uhde,
Johannesburg, South Africa
This
paper examines the practical application of the critical chain philosophy in
the project management of high value petrochemical projects.
1. INTRODUCTION
Krupp
Uhde is an Engineering Contractor operating in the Petrochemical field involved
in the design, procurement and construction of medium to large-scale
petrochemical plants for clients like Sasol. These contracts are in various
forms, usually Lump Sum Turn Key, but can also be reimbursable for and on
behalf of the client and various hybrids between the two. The Critical Chain
approach has been successfully applied on two contracts in our company with a
high degree of success. This paper highlights the transformation from where we
were, the successes, the problems, the lessons learnt and proposed future
improvements.
2. THE PROBLEM
As with all Project Management Companies the organisation sits with all
the age-old problems of managing contracts. These include:
·
Targets not met
·
Numerous changes (client and internal)
·
Tight budgets
·
Re-work and cost thereof
·
The conflict of time vs. money
·
Uncertainty factor in all aspects
resulting in misestimating, omissions and the unknown
·
High conflict environment (internal and
external with vendors, sub-contractors and with the client)
·
Highly chaotic environment
·
Project Managers accountable but with
limited line authority.
In our company these problems are usually addressed by sheer force of
management. Large amounts of overtime hours are worked to bring targets back on
track with the obvious associated negative financial implications. We are
forced to go to extreme lengths to eventually complete projects to the clients’
satisfaction with the obvious toll on personnel and cost. A major problem that
was being encountered on every project was that, although we had the most
fantastically detailed complicated schedules with all the sophisticated logic
links in place, these schedules were simply wrong. This is always discovered
too late. When for example it is discovered that a particular task has not been
started or completed because its predecessor information is not there, it is
too late do much about the situation. In the past we tried to address this by
insuring better involvement of the leads in the schedule to the point where
they were asked to sign and approve schedules before the start of the contract.
The problems persisted and solving of this problem, which is discussed in the
next chapter, was critical to the application of the critical chain process; as
without a correct schedule the process would be worthless.
How to solve the problem of the plan?
Marketing was selling projects with a schedule and as soon as all the
activities were applied the resultant conclusion always showed that the
contract could not be completed in the required time. Schedules were cut. This
meant we lost the buy in and commitment from the personnel in completing tasks
on time. This was further worsened by the fact that the logics in the schedule
were simply incorrect. This even after each discipline was completely involved
in drawing up the schedule. What was the problem? Were our people incompetent
or incapable of scheduling? Obviously not. Upon detail investigation into the
schedules it became obvious to me that the schedules were so complicated and
detailed it was impossible for anyone to understand all the links. Thus the
problem was in our approach in terms of the application of the detailed
activities. This was simply solved by starting with a simple graphic PERT
schedule of less than 100 activities to ensure all parties involved understood
the schedule and links. This ensured buy in from all parties and the correct
logic. The detailed activities are then added later by the specific disciplines
without affecting the logic.
Once we had an agreed schedule, all activities were cut throughout by 50%. An activity entitled critical chain float was added to the critical path at the end of the schedule. The duration allocated to this activity was half of what had been cut i.e. 25% of the entire project duration. The contract management team made themselves intimately aware of the critical path and set ourselves with two primary goals. These were to ensure that the critical path remained the same and that we would be as stingy as possible in terms of handing out critical chain float to the disciplines. This would ensure that we had some critical chain float left at the end of the project thereby ensuring that as a minimum a 25% overall improvement on the contract schedule would be achieved.
Weekly meetings were held between the planner, project manager and each discipline lead to assess progress and allocate critical chain float where required.
Another important step in the implementation was the workings with vendors and subcontractors. Our first major change, which has turned out to be one of the most important breakthroughs in the process, was during the enquiry stage. Instead of specifying a required delivery date for a piece of equipment, service etc. we simply requested the supplier to provide a best end date by which he could provide the goods or service. The importance of this step is that when in the past we provided a date we would hardly ever receive the goods on time because even if the vendor had plenty of time to do the work he would leave it right until the end (student syndrome) which meant that if something went wrong he could not fulfil his commitments. This we realised would result in a moving critical path, which we knew would be impossible to manage. The second important thing was that using this approach we could determine which goods and/or services were the constraints or bottlenecks. The narrowing down of these is crucial for the successful management of a contract as efforts can then be concentrated where they are most effective. The number we were left with that were critical even on the cut schedule turned out to be far less than anyone in our organisation would ever have imagined. The number was less than seven out of over one hundred suppliers on both the contracts where we used this approach.
Once we had identified the so called “bottleneck” vendors we called them in one by one and spent a long time selling them on the critical chain approach. This involved the cutting of their schedule, removal of penalties with regards the cut schedule, incentives and numerous other activities that could be the subject of a paper in their own right. The most important of these that does require mention here is the partnership approach. This allowed the supplier to set targets for certain deliverables from our side and if these were not met the equivalent time of the delay was added to their schedule from the critical chain float with no questions asked.
5. THE RESULT
The results of the process exceeded our expectations. The projects were
completed way ahead of schedule. Resource usage was significantly improved. The
relationship with suppliers was greatly improved to the point were integration
with certain key vendors was as if they were part of the same company. It was
as if a type of boundary less project team had been created which involved
several organisations all working toward the same goal.
Due the kitty of critical chain float available, internal relations
improved greatly. When a discipline was behind on a task due to just cause,
float was handed out on a common understanding without the pressure of having
to jump through hoops to achieve the unattainable. This pot of float turned out
to be a kind of potion to solve whatever problems we had on the contracts. In
the end the pot turned out to be significantly larger than required. Internally
the attitude of personnel also improved dramatically on the projects. The in
and out box syndrome was greatly reduced due to improved proactiveness by
individuals. This made discipline interfaces much improved. The project
organogram became less formal as all individuals became more goal orientated.
Personnel now tended to build on each other’s strengths and cater for what
weaknesses existed. Conflict was almost entirely eliminated.
Specific results on the contracts worked on:
High Purity Ethanol
·
Contract completed in 16 months vs.
industry norm of 24 months
·
No late equipment deliveries (never
before achieved in our organisation)
·
Great improvement on envisaged profit
at contract award (figures unavailable due to confidentiality)
·
Reports from suppliers that they also
experienced improved profitability.
NMP Gum Removal
A special mention concerning the background of this project is required.
A certain side stream from a new plant at Sasol in Secunda was being fed back
into one of their refinery plants. Unfortunately a contaminant in this stream
was damaging the catalyst and resulting in the catalyst having to be
regenerated several times a month instead of annually, as was the norm. The
losses due to the direct costs as well as the downtime was in the order of
several hundred thousands of rand per day.
This was a perfect case study for the critical chain approach as due to
the financial pressure there were none of the conventional constraints.
The results:
·
Contract complete in 4 month including
working over the Christmas period vs. an industry norm of 12 months for a plant
of this size. This is phenomenal when one considers that the conventional
equipment delivery time for a large distillation column, which was part of the
plant, is 9-10 months.
·
New innovative fast track design
methods were implemented.
6 LESSONS LEARNT
·
Always start with a simple plan.
·
Do not allow the momentum of a large
project lull you into a false sense of security in terms of progress. A large
project is like a large ship with a huge amount of momentum, once you are going
in the wrong direction it is very difficult to steer onto the right course. The
critical chain approach makes for easy steering.
·
Identify critical path and manage to
keep one critical path.
·
Identify “bottleneck”
vendors/sub-contractors early on.
·
Do not fast track by traditional
methods like early orders and start of construction before you know what to
order and what to build. These methods give a false sense of security in terms
of schedule progress. The true result of such steps is the snowballing of
errors that will exist in any project. It is cheaper and quicker to fix
something on paper than in concrete and steel.
·
Give change management the highest
priority.
7 FUTURE DEVELOPMENTS/GOALS
·
Application of critical chain process
to multi projects.
·
Convince organisation and client to accept
different reporting on progress i.e. rate of consumption of critical path float
vs. weighted progress.
·
Create project incentives for team
members related to project goals.
·
Change organisational procurement
conditions to exclude penalties and move to incentive based contracts with
suppliers and sub contractors.
6. CONCLUSION
Critical Chain Project Management is logical and practical approach to
managing projects that has certainly proved its worth in our organisation. The
field of application in our business is large and what has been applied to date
is only a fraction of the scope of application.
Author: Brandon Loots holds a
B.Sc. Chemical Engineering from the University of the Witwatersrand. At present he is the Project Director on a
large multi national project for Sasol. He leads a Joint Venture between Krupp
Uhde and Mitsubishi Chemical Engineering Corporation of Tokyo.
Presenter:
The paper is presented by Brandon Loots.